Page1of30TECHNICAL SPECIFICATIONS FOR IP CCTV SURVEILLANCE SYSTEM, ACCESS CONTROL SYSTEM (ACS), BOOM-BARRIER AND TURNSTILE. ---------------------
Page10of30TECHNICAL SPECIFICATIONS: (I) IP CCTV SURVEILLANCE SYSTEM : (a) IP Video System Overview: • Transmit and Receive H.264 and MPEG-4 Vi
Page11of30• Each of these streams must be independently configurable to view and record at different frame rate and resolutions simultaneously.
Page12of30• Latest Sony Ex View HAD 1/3” or 1/4" imager or better • Camera must provide at least 752x582 (PAL) active pixels • Color Re
Page13of30• Each stream Bit-rate should be user configurable from 32 to 4096 Kbps • The IP Camera will have a built in web server, making it ac
Page14of30(d) IP Fixed Dome Camera (Indoor Type) • Latest Sony Ex View 1/3 “ or 1/4" interlaced imager or better • Camera must provide at
Page15of30• Must have minimum 1 alarm inputs and 1 relay outputs • The IP Camera must support redundant recording by streaming to multiple rec
Page16of30- Drag & Drop functions for most functions on the system and also for set up of connection between cameras and monitors and also s
Page17of30• The software should be capable of monitoring the status of any camera in the network and should indicate when a device goes offline
Page18of30 (II ) 5 KVA UPS (ONLINE) WITH BATTERY BACKUP FOR 30 MINUTES : Application: Power supply requirement for IP CCTV, Access Control syst
Page19of30• Indication: Mains ON, Inverter ON/ OFF/ Faulty, Battery level, Static bypass on, Load level, over temperature • Audible alarm: Main
Page2of30DESIGN CONCEPT & SCOPE OF WORK : 1) IP CCTV SURVEILLANCE SYSTEM (i) DESIGN CONCEPT: • The entire IP surveillance system is de
Page20of30(V) ACCESS CONTROL SYSTEM : (a) Single Network Controller/Reader 1. The network controller/reader shall provide access control proce
Page21of30c. Operating Temperature: 32° to 122° F (0° to 50° C) d. Humidity: 5% to 95% relative, non-condensing e. Visual Indicators: 1. Syste
Page22of30• Displays history of all logs. • Configurable number of transactions on monitor window. • Emergency message display. • Set up rules
Page23of30(vi) Schedule Management • Set Schedule for Employees as to when they can access the various Areas. • Set Holiday Lists for the Emplo
Page24of30• Manpower planning assists to generate date wise plan to set shift, shift sequence, leaves, overtime. • Leave management module allo
Page25of30( VI) BOOM-BARRIER: (a) Boom - Barrier : • Installation: outdoor • Drive: Electric motor • Power supply: 230+/- 10% VAC, 50 Hz • Fi
Page26of30Loop installation: • Barrier installations which close automatically utilize induction loops, to detect approaching vehicles. • The l
Page27of30 (VIII) Bidder to submit the following documents / confirmations along with bid documents. (1) Bidder must submit separately clause w
Page28of30LIST OF INDICATIVE MAKES The following is the list of products and indicative makes. Bidder is free to propose any other equivalent M
Page29of30C. Boom-Barrier and Turnstile 1 Boom Barrier Came/FAAC/ Automatic Sytems/Magnetic Control 2 Electro-mechanical Turnstiles Came/FAAC/
Page3of30• Provide supervisory specialists and technicians at the job to assist in all phases of system installation, start up and commissioning
Page30of30DRAWINGS/ DOCUMENTS LIST SR. NO. DESCRIPTION DRAWING NO. 01 LAYOUT, BUILDINGS CO-ORDINATES PLAN CDRI/LKW/499/A1W-043 02 I
Page4of30 2) ACCESS CONTROL SYSTEM (ACS): (i) DESIGN CONCEPT • Access Control System is designed for the entrances and corridors of main buil
Page5of30• The ACS shall be a software-based solution and shall be flexible enough to work with multiple Hardware providers. The software shall
Page6of30 3) BOOM-BARRIER AND TURNSTILE: (i) DESIGN CONCEPT Gate automation system proposed for CDRI Campus consist of Boom Barrier & turns
Page7of30• The price coated by the vendor should include all the expenses incurred in commissioning of gate automation System, comprising of boo
Page8of30(4) SUBMITTALS: ( IP CCTV, Acess Control System, Boom Barrier and Turnstile) (i) Drawings: The system supplier shall submit all shop dr
Page9of30(6) TESTING: • Component Testing: Maximum reliability shall be achieved through extensive use of high-quality, pre-tested components. E